How will the roundabout be constructed?

The contractor will build the roundabout when part of the highway is closed to traffic. Highway 41 will be closed between Hazeltine Blvd and just north of Peavey Rd for up to 3 months. Construction is scheduled to begin in spring 2023. Specific dates for the road closure will be shared as soon as the information becomes available.